Casos de Éxito

Coca-Cola Chihuahua

Coca-Cola Chihuahua grows and improve his production capacity to fill market demand
  • Origins
  • Arca installed a new non-returnable packing line within the plant RIMAC in Lima, Perú. Electro helped with AC to move the line to Lima to install it in Chihuahua.
  • Solution proposal
  • Electro participated with the expert engineering team of Arca Continental in the next periods of the project:
  • -Transfer to Lima, Peru
  • -Unloading and armed of Chihuahua
  • -Support with the car manufacturers for their maintenance
  • -Installation of services (water, air, syrup, CO2, etc)
  • Results
  • It was achieved the consolidate the production capacity of the plant in Chihuahua, by means of
  • -Use of existing assets
  • -Growth of the electric substation
 